Limousin Living
Living and Building a home in the heart of France
19th October 2005
Display Menu
Shutters
Meanwhile... the shutters are installed!
Two lads came to drill holes in the blockwork, fix hinges with epoxy resin and hang the shutters. No doubt they'll be taken off again when the walls are rendered, but they do make the house look closer to completion.
Another delivery brings electrical materials, including a great stack of conduit already threaded with cables, already connected up to distribution boxes, labelled and coded according to the plan, ready to go!
Monsieur Trichard came again yesterday to check on work in progress. He says the carpenters are coming back "next week" to correct the
Roof Problem.
That means they'll have to do it all from outside, since the ceiling has been built underneath it....